Queensway Health Centre

Contract Administrator – Hertfordshire NHS Trust

Programme of Works – 25 weeks

Project Value - £330,000

This was a live working Health Centre, where works were completed during COVID-19. We liaised well with the client and staff on site. We remained on schedule and completed on time.

The works included the construction of a new external disabled lift shaft to provide access to the first floor of the building for wheelchair users, and the supply, installation and commission of a new passenger lift. The creation of a new buggy store. Upgrading the existing side entrance of the building. Associated external works and drainage. New brick and blockwork was formed to create a new lift shaft. A single ply Bauder roofing system was installed. We also installed aluminium rainscreen cladding, roof structures to include fascias and soffits.

We also completed external groundwork which included foundations to install a disabled ramp access with curbs, edging, channels, paving accessories, handrails and illuminated external signage. We also provided COVID-19 related works.

The following works for this included:
Demolition of existing partition walls, ceilings, and isolations for M&E to receive new alterations to form the COVID-19 patient ward. Supply and install new partitioning, tape and jointed and decorated. New white roc wall system was applied to various areas. Vinyl flooring and suspended ceilings. First fix and second fix M&E which included new lighting, emergency pull cord, fire signage system and access control.